Question 1 of 5
Collaboration with StakeholdersMidway through a sprint, a sales VP asks the Scrum team to add a new dashboard filter "urgently" for next month's planning meeting. When the business analyst asks, the VP confirms that nothing stops working without the filter and that the meeting is five weeks away. What should the business analyst recommend?
Show the answer and explanation
Correct answer: D. Put the request on the product backlog to prioritize for a later sprint
Before treating new work as urgent, the team asks whether it is business-stopping and how long the stakeholder can wait; here nothing stops and the meeting is weeks away. Scrum discourages mid-sprint interruptions, so the request goes on the product backlog to be prioritized for a later sprint. Moving to Kanban is the most tempting wrong choice, but Kanban does not help a team if the work is not really interruption-driven.
Read from the source: Choose the Best Workflow